# Gantt chart

Gantt chart draws one bar per task between its start and end dates, so you can see a schedule and how its tasks overlap.

## Lay out a small website project

Five tasks run through March 2026, from Plan to Launch. Build, on March 5 to 10, overlaps with both Design and Test, which the bars show at a glance.

Result
| Task | Start | End |
| --- | --- | --- |
| Plan | 2026-03-02 | 2026-03-03 |
| Design | 2026-03-04 | 2026-03-06 |
| Build | 2026-03-05 | 2026-03-10 |
| Test | 2026-03-09 | 2026-03-11 |
| Launch | 2026-03-12 | 2026-03-13 |

1. Open the dropdown at the top of Properties. It shows `Gantt chart`. Choose `Event timeline`. The tasks now appear as dated callouts on a spine.
2. Go back to `Gantt chart`. In the Data tab, change Task, Start or End (optional) to use other columns.
3. Open the Design tab and expand Bars and layout to adjust the rows.

## When to use

Use Gantt chart for a schedule where tasks have a duration, so you can see what runs at the same time. If each entry has only one date, use Event timeline, which leaves more room for text.

## Inputs

1 port

**Table**

Accepts: Tables.

Accepts one connection on this port.

## Settings

An empty End makes milestones, and rows with a null date are left out. An interval that ends before it starts raises an error.

**Start**

Date column for the task start, event date or calendar day. Auto picks one.

**Operation**

Whether a task starts at the earliest or latest date in its rows.

Default: `Earliest`

Options: Earliest, Latest.

**Task**

Column that names each task or event. Auto picks a readable one.

**End (optional)**

Column with each task's end date. Leave empty to show each task as a milestone.

**Group by**

Optional column that groups tasks or colors events.

24 more settings

**Source timezone**

IANA time zone for timestamps without an offset, such as Europe/Copenhagen. Ambiguous local times need an explicit offset.

Default: `UTC`

**Chart timezone**

IANA time zone used for grouping and display. Vista filters keep their own time zone.

Default: `UTC`

**Week starts**

Day the week starts on.

Default: `Monday`

Options: Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday.

**Fiscal year starts**

Month the fiscal year starts in. Sets quarter and year boundaries.

Default: `January`

Options: January, February, March, April, May, June, July, August, September, October, November, December.

**Sort by**

Order of the tasks or events, chronological by default.

Default: `Default (chronological)`

Options: Default (chronological), Start, End, Duration, Task, Group, Rows.

**Date labels**

How dates are written in the chart labels.

Default: `Auto`

Options: Auto, Iso, Date, Datetime, Custom.

**Tooltip dates**

How dates are written in tooltips.

Default: `Iso`

Options: Auto, Iso, Date, Datetime, Custom.

**Show tooltip**

Shows or hides values when you hover over a mark.

Default: `true`

**Tooltip**

Text shown when you hover over a mark. Write it in the editor and insert values from Values.

**Values**

Values you can insert into the text. Each row calculates a value from a source field or, in charts, shows a chart value, and can have its own number or date format.

**Title**

Title shown inside the chart. Leave empty to hide it.

**Title color**

Color of the title.

**Title size**

Size of the title, in pixels.

Default: `24`

**Title alignment (plot)**

Alignment of the title.

Default: `Left`

Options: Left, Center, Right.

**Bar labels**

Shows or hides task durations on the bars.

Default: `Duration`

Options: Duration, Off.

**Duration unit**

Unit for bar duration labels.

Default: `Auto`

Options: Auto, Days, Weeks, Months.

**Bar label size**

Size of the duration labels, in pixels.

Default: `9`

**Bar label color**

Color of the duration labels.

**Row gap**

Space between task rows, as a percent of each row (0–80).

Default: `20`

**Max bar height**

Thickest a bar can be, in pixels. Leave empty for auto.

Default: `24`

**Background**

Card background color. Auto follows the theme.

**Plot padding**

Space between the card edge and the chart, in pixels.

Default: `0`

**Corner radius (px)**

Corner radius in whole logical pixels.

Default: `0`

**Border width (px)**

Border width in whole logical pixels.

Default: `0`

## Gantt chart FAQs

**What if a task has no end date?**

Leave End empty to show every task as a milestone, drawn as a diamond. If End is set, a row with no end date is left out.

**What do swimlanes do in a Gantt chart?**

Choosing a Group by groups the tasks into lanes and adds a summary bar per group that spans its tasks.