    Gantt chart draws one bar per task between its start and end dates, so you can see a schedule and how its tasks overlap.

    Lay out a small website project

    Five tasks run through March 2026, from Plan to Launch. Build, on March 5 to 10, overlaps with both Design and Test, which the bars show at a glance.

    The live example needs a desktop screen. The result it produces is shown here, and the explanation and settings below work on any screen.

    Result
    TaskStartEnd
    Plan2026-03-022026-03-03
    Design2026-03-042026-03-06
    Build2026-03-052026-03-10
    Test2026-03-092026-03-11
    Launch2026-03-122026-03-13
    1. Open the dropdown at the top of Properties. It shows Gantt chart. Choose Event timeline. The tasks now appear as dated callouts on a spine.
    2. Go back to Gantt chart. In the Data tab, change Task, Start or End (optional) to use other columns.
    3. Open the Design tab and expand Bars and layout to adjust the rows.

    When to use

    Use Gantt chart for a schedule where tasks have a duration, so you can see what runs at the same time. If each entry has only one date, use Event timeline, which leaves more room for text.

    Inputs

    1 port
    Table

    Accepts: Tables.

    Accepts one connection on this port.

    Settings

    An empty End makes milestones, and rows with a null date are left out. An interval that ends before it starts raises an error.

    Start

    Date column for the task start, event date or calendar day. Auto picks one.

    Operation

    Whether a task starts at the earliest or latest date in its rows.

    Default: Earliest

    Options: Earliest, Latest.

    Task

    Column that names each task or event. Auto picks a readable one.

    End (optional)

    Column with each task's end date. Leave empty to show each task as a milestone.

    Group by

    Optional column that groups tasks or colors events.

    24 more settings
    Source timezone

    IANA time zone for timestamps without an offset, such as Europe/Copenhagen. Ambiguous local times need an explicit offset.

    Default: UTC

    Chart timezone

    IANA time zone used for grouping and display. Vista filters keep their own time zone.

    Default: UTC

    Week starts

    Day the week starts on.

    Default: Monday

    Options: Monday, Tuesday, Wednesday, Thursday, Friday, Saturday, Sunday.

    Fiscal year starts

    Month the fiscal year starts in. Sets quarter and year boundaries.

    Default: January

    Options: January, February, March, April, May, June, July, August, September, October, November, December.

    Sort by

    Order of the tasks or events, chronological by default.

    Default: Default (chronological)

    Options: Default (chronological), Start, End, Duration, Task, Group, Rows.

    Date labels

    How dates are written in the chart labels.

    Default: Auto

    Options: Auto, Iso, Date, Datetime, Custom.

    Tooltip dates

    How dates are written in tooltips.

    Default: Iso

    Options: Auto, Iso, Date, Datetime, Custom.

    Show tooltip

    Shows or hides values when you hover over a mark.

    Default: true

    Tooltip

    Text shown when you hover over a mark. Write it in the editor and insert values from Values.

    Values

    Values you can insert into the text. Each row calculates a value from a source field or, in charts, shows a chart value, and can have its own number or date format.

    Title

    Title shown inside the chart. Leave empty to hide it.

    Title color

    Color of the title.

    Title size

    Size of the title, in pixels.

    Default: 24

    Title alignment (plot)

    Alignment of the title.

    Default: Left

    Options: Left, Center, Right.

    Bar labels

    Shows or hides task durations on the bars.

    Default: Duration

    Options: Duration, Off.

    Duration unit

    Unit for bar duration labels.

    Default: Auto

    Options: Auto, Days, Weeks, Months.

    Bar label size

    Size of the duration labels, in pixels.

    Default: 9

    Bar label color

    Color of the duration labels.

    Row gap

    Space between task rows, as a percent of each row (0–80).

    Default: 20

    Max bar height

    Thickest a bar can be, in pixels. Leave empty for auto.

    Default: 24

    Background

    Card background color. Auto follows the theme.

    Plot padding

    Space between the card edge and the chart, in pixels.

    Default: 0

    Corner radius (px)

    Corner radius in whole logical pixels.

    Default: 0

    Border width (px)

    Border width in whole logical pixels.

    Default: 0

    Gantt chart FAQs

    What if a task has no end date?
    Leave End empty to show every task as a milestone, drawn as a diamond. If End is set, a row with no end date is left out.
    What do swimlanes do in a Gantt chart?
    Choosing a Group by groups the tasks into lanes and adds a summary bar per group that spans its tasks.